Endeavour (OV-105)

Background

Upgrades and Features

Construction Milestones

07/31/87 Contract Award
02/15/82 Start structural assembly of Crew Module (yes 1982)
09/28/87 Start structural assembly of aft-fuselage
12/22/87 Wings arrive at Palmdale from Grumman
08/01/87 Start of Final Assembly
07/06/90 Completed Final Assembly
04/25/91 Rollout from Palmdale
05/07/91 Delivery to Kennedy Space Center
04/06/92 Flight Readiness Firing
05/07/92 First Flight (STS-49)

The orbiter Endeavour underwent a 8-month Orbiter Maintenance Down Period (OMDP) in Palmdale, CA. The most significant modification will be in the installation of an external air lock making Endeavour capable of docking with the International Space Station once construction begins late 1997. (Reference KSC Shuttle Status 7/30/1996).

Endeavour's Flights to date:

01. STS-49 (05/07/92)
02. STS-47 (09/12/92)
03. STS-54 (01/13/93)
04. STS-57 (6/21/93)
05. STS-61 (12/02/93)
06. STS-59 (04/09/94)
07. STS-68 (9/30/94)
08. STS-67 (3/02/95)
09. STS-69 (9/07/95)
10. STS-72 (1/11/96)
11. STS-77 (5/19/96)

OMDP to Palmdale

12. STS-89 (1/22/98)

13. STS-88 (Estimated 7/9/1998)
14. STS-96 (Estimated 12/3/1998)
15. STS-98 (Estimated 5/13/1999)
16. STS-101 (Estimated 9/16/1999)

Endeavour's Flight Logs to date:

12 flights
xxx Million Miles
xxx orbits
xxx days in space